Diesel and energy budget of a routing

Expert

The essentials

A routing that runs the engine can tell you how much diesel it burns and what is left in the tank at the finish. If you also describe the boat’s electrical consumption and its charging sources, it follows the charge of the batteries hour by hour as well and counts the engine hours needed to recharge them.

  1. In “Settings”, “My Boat”, fill in the “Engine” section (diesel consumption, tank capacity). For the energy budget, fill in the “Energy” section too.
  2. In “Settings”, “Routing”, set “Tank level at the start” and “Batteries at the start”. For the routing to motor, turn on “Allow engine use” (see Routing settings).
  3. Calculate the routing, then open its “Statistics” tab: see Read a routing.

The diesel appears as soon as the routing has run the engine, to make way or to charge the batteries. Each routing keeps the values it was calculated with: changing the consumption or the tank afterwards does not change its results.

Going further

The engine: “Settings”, “My Boat”, “Engine” section

SettingUseDefault
“Motoring speed”the boat’s speed under engine; the same setting as in “Routing”6.0 knots
“Diesel consumption”litres (or gallons, per “Settings”, “General”, “Units”, “Volume”) per hour at that speed, from 0 to 200 in steps of 0.11.7 L/h
“Tank capacity”the usable volume of the tank, from 0 to 10,000 L60 L

The energy budget: “Settings”, “My Boat”, “Energy” section

Powers are given in watts. On a 12 V boat, multiply amps by 12 (5 A is 60 W). The budget exists only if “Draw by day” or “Draw at night” is above 0: with both at 0, the routing calculates no energy.

SettingUseDefault
“Battery bank”the bank’s capacity, in Ah under 12 V (10 to 5,000)200 Ah
“Maximum discharge”how low the bank may go before being recharged (10 to 90 %); about 50 % for lead or AGM, 80 % for lithium50 %
“Engine charges up to”where the engine stops charging (50 to 100 %); about 85 % for lead or AGM, the last per cents going in at a trickle, 95 % for lithium85 %
“Draw by day”what the boat draws on average by day (autopilot, instruments, fridge), from 0 to 3,000 W0 W
“Draw at night”the same at night, navigation lights included0 W
“Charging under engine”what the alternator really puts into the batteries, often half of its rating (0 to 5,000 W)400 W
“Diesel charging in neutral”litres per hour when the engine only charges, about half of what it burns under way1.0 L/h
“Solar panels”their peak power, in Wp (0 to 5,000)0
“Hydrogenerator at 10 kt”its power at 10 knots through the water (0 to 3,000 W)0 W
“Fuel cell”its power (0 to 2,000 W)0 W

In the application these settings are written on two lines: “Engine charges up to”, for example, reads “Engine charges” then “up to”.

The starting point: “Settings”, “Routing”

  • “Tank level at the start”: the level of the tank at the start, as a percentage of its capacity (100 % by default).
  • “Batteries at the start”: the charge of the batteries at the start, as a percentage of the bank (100 % by default, right for a start from a harbour).

Both settings stay as you left them until you change them. When the routing starts from the boat’s position (“Now from my position”) and the energy budget is filled in, NavimetriX reads the charge of the lowest bank from the instruments and writes it into “Batteries at the start”. With no charge received from the instruments, the value of the setting is kept.

How the calculation follows the batteries

The routing follows the charge hour by hour, from the starting charge.

  • The sources. The sun depends on the height of the sun along the route (panels laid flat) and drops under the clouds when the forecast has them. The hydrogenerator gives its power at 10 knots, much less when slower, nothing under 3 knots nor while the engine runs. The fuel cell covers what the other sources leave missing. While the routing motors, the alternator charges too.
  • The ceiling. What is produced beyond a full charge is lost.
  • The floor. When the charge reaches the “Maximum discharge”, the engine starts and charges up to “Engine charges up to”; the sun and the hydrogenerator fill on above it.

Where to read the result

  • “Statistics” tab, “Motoring” tile: the engine time (route and charging), the consumption (“at … under way, … charging”), the “Diesel” burnt and what is “Left at the finish”, in volume and as a percentage of the tank, or “empty”. “Energy” tile: the energy drawn (“… kWh drawn”), the bank and its floor, then “Batteries at the start”, “Charging under engine” (duration and diesel), “Engine for the batteries” (per day, over more than a day), “Lowest charge” with its time and “Not covered (no charging power)” when there is not enough to charge with.
  • “Points of attention”: “Low on diesel” under 10 % of the tank, “Tank empty” when diesel is missing at the finish. The routing then keeps motoring: it says how much is missing.
  • “Route profile”: an “Energy” lane (coloured bars by source: “Sun”, “Hydrogenerator”, “Motoring on the route”, “Fuel cell”, “Charging under engine”, with the “Draw” curve) and a “Batteries” lane (the charge and the “Lowest allowed” floor).
  • “Charging schedule”: one line per day on which the engine charges the batteries, with the columns “Charging under engine” (from what time to what time), “Hours”, “Diesel” and “Lowest charge”.
  • Routing table: a “Diesel used” column, the diesel burnt since the start.
  • PDF report: the same figures, the profile and the charging schedule.

In a “Compare” series, the comparison adds a “Diesel” column: see Compare routings.

See also